Sample lead time, production lead time, and what a paid sample buys
2026-10-28
A sample in ten days and a production run in thirty days are ordinary figures, and buyers often read them as the same clock with a different start. They are not. A sample is made by a different route: a small batch, a short run on a press that would otherwise be idle, and a finishing batch that may share a line with other work in the shop.
The sample clock starts when the drawing and the finish are agreed and the sample fee is received, not when the enquiry arrives. If the finish is a new colour, add time for a colour match. If the piece needs a new tool, add the tool build before the first part exists at all. A ten-day sample usually means an existing tool and a standard finish.
The fee normally covers the material, the press time, the finishing batch, the packing and the courier. It does not normally cover the tool, which is quoted separately and stays with the factory. A sample fee is a charge for a small production run, and it is priced higher per piece than the bulk order because the setup is spread over one or two pieces instead of thousands.
Ask what happens to the fee afterwards. Some factories credit it against the first order above a stated quantity; some do not. Ask before you pay, and ask in writing. Also ask whether the sample is made on the production tool or on a sample tool, because a part from a sample tool can differ in a radius or a fit from the part that ships.
Production lead time starts later than most buyers expect. It starts when the deposit is received and the pre-production sample is signed, and it runs through material purchase, press scheduling, finishing, inspection and packing. Plating is often the bottleneck, because parts queue for a full batch and a small order waits until there is enough work to fill the bath.
A realistic split for a repeat order on an existing tool with a standard finish is a few days for material, one to two weeks on the press, about a week in finishing, and a few days for packing and inspection. New tooling adds its own weeks in front of that. The container schedule is set after packing is complete, not before.
The useful question is not how long the lead time is but what has to be true before the clock starts. Get the answer in writing: which sample, which finish, which quantity, which port. A supplier who can name the dependencies is easier to plan around than one who quotes a single number and then explains the delay afterwards.